Vacaville, CA
This five story, 300,000 square foot manufacturing facility is the largest pharmaceutical manufacturing plant on the West Coast. The project required extensive coordination and planning to work within the constraints of the site. REG utilized just-in-time deliveries and worked with 3D modeling software to find conflicts early on during the design process.
The entire project was completed using an accelerated 15-month schedule. In addition, part of the project was constructed within an operating facility and had to be performed without disrupting ongoing operations. The central utility plant, which affects all of the systems Genentech uses to produce its validated biopharmaceutical drugs, was doubled in size.