San Jose, CA
The Equinix SV-5 Data Center is a fast-track project that consists of a 185,000 square foot building on a greenfield site. The scope of work includes the installation of a critical power system infrastructure including a primary utility service, (4) 5000A 480 volt services and (4) 3000kW generators. When completed, the project will total approximately 100,000 square feet of data floor.
The project schedule consists of a 6-month construction schedule and an xtensive BIM/3D modeling for coordination.