Santa Clara, CA
The CoreSite Santa Clara Data Center project was a fast-track project that consisted of a 101,000 square foot building, divided in (6) customer rooms. The scope of work included theinstallation of a critical power system infrastructure with a primary utility service, backed up by (4) 2-Megawatt generators in the first phase. All conduits were installed to minimize setup time for future phases.
The project was completed in less than 6 months, including coordination with public utility and an extensive BIM/3D modeling for coordination.